NEC ECC: No work on programme

0 votes
57 views
The Contractors 1st programme shows a few "no work days for the main gang" items as their subcontractor needs the space. The Contractor then programmes in other work. As the programme is subject to change. If the subcontractor completes early. Can the client insist our main gang work on the "no work days" ?
asked Feb 9 in Time by J (590 points)  

1 Answer

0 votes
 
Best answer
No the Client  can not "insist" as it is your programme and your prerogative as to how you do the works efficiently for yourself whilst meeting any contractual deadlines. They may question why you wouldn't, but you would assume you have your reasons otherwise surely you would.
answered Feb 9 by Glenn Hide Panel Member (82,630 points)  
selected Feb 9 by J