Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,598 questions

6,007 answers

1,384 comments

Register its Free

Download here

NEC ECC: No work on programme

0 votes
56 views
The Contractors 1st programme shows a few "no work days for the main gang" items as their subcontractor needs the space. The Contractor then programmes in other work. As the programme is subject to change. If the subcontractor completes early. Can the client insist our main gang work on the "no work days" ?
asked Feb 9 in Time by J (570 points)  

1 Answer

0 votes
 
Best answer
No the Client  can not "insist" as it is your programme and your prerogative as to how you do the works efficiently for yourself whilst meeting any contractual deadlines. They may question why you wouldn't, but you would assume you have your reasons otherwise surely you would.
answered Feb 9 by Glenn Hide Panel Member (82,550 points)  
selected Feb 9 by J