Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,617 questions

6,029 answers

1,389 comments

Register its Free

Download here

NEC ECC: Acceleration and delay damage entitlement

0 votes
51 views
Nec 3: Option A: when accepting a quotation for acceleration the contract allows amendment of the prices, completion date and key dates, as given in clause 36.3. Question: would the date for liquidated damages automatically move forward with the new Completion Date ?
asked Feb 7 in Time by engineering (350 points)  

1 Answer

0 votes
Yes it would so  the Contractor needs to price the increase risk of delay damages for an earlier Completion Date with an acceleration quotation. That is the reason that a Project Manager can not make their own assessment of a Contractor acceleration quotation - it has to be by agreement.
answered Feb 7 by Glenn Hide Panel Member (82,630 points)