A test or inspection done by the Supervisor has caused unnecessary delay. Is this a compensation event?

0 votes
347 views

A test or inspection done by the Supervisor has caused unnecessary delay. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

This is a compensation event (see Clause 60.1(11)). The Supervisor’s tests and inspection work must be done “without causing unnecessary delay” (see Clause 40.5).