Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,598 questions

6,007 answers

1,384 comments

Register its Free

Download here

NEC SC: Subcontractors

0 votes
162 views
We are on a large Supply Contract which is for fabrication of items for another site. Our opinion is that Supply contract is the wrong option but that's what we have to work with. The Z clauses have amended the Subcontract section to state that we have to submit NEC 'type contracts' for review prior to commencing. As there is no Supply Subcontract can we amend a supply contract to suit a subcontract or is it best to use a Option A Subcontract and amend the clauses to match the Z clauses and such that we have to flow down?
asked Jan 10 in General by WatersideSurveyor (890 points)  

1 Answer

0 votes
 
Best answer
You have to engage your subcontractor under what you consider to be the correct set of rules of engagement for them to fulfil their obligations and meet your required risk profile. I would generally say you would use the Supply Contract and either amend it to a subcontract version, or have a statement that where it says Supplier it means Subcontractor (or Subsupplier?) and where it says Purchaser it should read as Supplier. You may also need to change some of the timescales so they have less time to do something so you have their submission before you can add to it and submit up as your submission (e.g. period to produce a compensation event quotation you need quicker from them to produce your own quote). In most instances you want to be back to back under similar terms/rules.

I do take your point here though that you feel the Supply Contract was not the right contract. If for your example your Subcontractor is doing an element of supply AND install, then you may well be correct that you should consider using an option A contract down the line even if you are under what you consider to be the wrong type of contract. The important thing is that either way you will be back to back under an NEC type of contract, so language and principles will all be similar.
answered Jan 10 by Glenn Hide Panel Member (82,550 points)  
selected Jan 10 by WatersideSurveyor
Thanks as ever Glenn. 12 years in and still learning.
Every day is a school day - and that is the same for us as panel members!