NEC ECC: Is equipment a potential disallowed cost ?

0 votes
60 views
NEC3 ECC (option E), clause 11.2. (25) gives items which could fall under disallowed cost. This clause specifically mentions: plant, materials and resources. Equipment (diggers, dumpers, temp works etc) is not mentioned, hence is unproductive equipment at risk of disallowed cost? I assume it is and is classed as “resources” ?
asked Jan 10 in General by engineering (220 points)  

1 Answer

0 votes
The term 'resources' is not defined and could include Equipment.  Interestingly this bullet point could also include Plant and Materials as the caveat in the previous bullet point is different and relates to different circumstances.
answered Jan 14 by Andrew W-I Panel Member (25,540 points)