Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,760 questions

6,178 answers

1,431 comments

Register its Free

Download here

NEC3 ECC: Fees applied under ECI Stage One - Option C, WAO/H or People OH?

0 votes
146 views
We are under contract with a Subcontractor on a two stage contract, using the NEC3 ECI addendum, Option C.

Stage One applications are being submitted by the Subcontractor applying People Overhead for People costs, and Direct Fee to People and other categories.

No target has yet been agreed (part of Stage One WI), and final ECI cost will form part of the eventual agreed target.

With this in mind, I am of the opinion that Working Area Overhead should be applied to People costs in Stage One applications, not People Overhead?

Any advice would be appreciated
asked Nov 26, 2019 in Payment by BJM_2019 (120 points)  

1 Answer

+1 vote
When reimbursing the (Sub)Contractor's Defined Costs under options C, D or E, the full Schedule of Cost Components is always used (and it is the default for assessing compensation events unless it is agreed to use the Shorter Schedule).

Consequently, throughout the duration of the contract, it should be the WA OH% that is applied to People costs.
answered Nov 27, 2019 by Jon Broome Panel Member (64,230 points)  
Thanks for your response Jon.