Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,868 questions

6,316 answers

1,502 comments

Register its Free

Download here

The Supervisor has instructed the Contractor to search for a defect and no defect is found but the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Is this a compensation event?

0 votes
349 views

The Supervisor has instructed the Contractor to search for a defect and no defect is found but the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The event is not a compensation event (see Clause 60.1(10)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)