The Supervisor has instructed the Contractor to search for a defect and no defect is found but the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Is this a compensation event?

0 votes
343 views

The Supervisor has instructed the Contractor to search for a defect and no defect is found but the search is needed only because the Contractor gave insufficient notice of doing work obstructing a required test or inspection. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The event is not a compensation event (see Clause 60.1(10)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)