Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,752 questions

6,169 answers

1,429 comments

Register its Free

Download here

NEC ECC: Can the value of an implemented CE be changed by agreement between the parties?

0 votes
128 views
Can the value of an implemented CE be changed by agreement between the parties if it is subsequently determined that the agreed amount was wrong and both parties agree that is the case.
asked Nov 3, 2019 in Compensation Events by IRB (160 points)  

1 Answer

+1 vote
There is no express provision allowing this.

However, it is implied in the contract because there is a compensation event for a changed decision by the Project Manager or the Supervisor - see clause 60.1(8). Note that it only allows for the Prices to go up and no compensation event can bring forward (sectional) Completion Date(s).

If this was what was desired then, strictly by the contract, you would need a Supplementary Agreement to reduce the Prices & Completion Date(s).
answered Nov 4, 2019 by Jon Broome Panel Member (64,190 points)