NEC ECC: Dealing with numerous low value CEs efficiently

0 votes
82 views
What options exist for the Contractor and Project Manager to agree a large number of low-value CE's simply in a ECC Option B Contract?
asked Nov 3 in Compensation Events by IRB (160 points)  

1 Answer

0 votes
1. PM states as a PM assumption when instructing a quotation for each and every one something like "Evaluate on the basis that there is no delay and disruption for this compensation event and, if there is, this is assessed together with delay and disruption from other similarly worded compensation events in the same month.
2. Assess direct costs for each compensation event.
3. At the end of the month, have a wrap up compensation event for delay and disruption in that month under clause 60.1(17) for changed assumptions.
answered Nov 4 by Jon Broome Panel Member (59,440 points)