Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,315 questions

5,695 answers

1,260 comments

Register its Free

Download here

NEC ECC: Option A - Contract Data Part 2

0 votes
123 views
How do we recover Designers time when their rates are not included within our CD2 ?
asked Oct 5 in Contract Data by GaryC (140 points)  

1 Answer

0 votes
Under main Option A this situation would only be applicable to a compensation event.

If no rates are stated in Contract Data Part 2 and the designer is a consultancy then you could treat them as a Subcontractor.

If the designer's are employees of the Contractor then they would be classed as People, although if they are not working in the Working Areas then you would need to add an area to the Working Areas to ensure their cost can be treated as Defined Cost.
answered Oct 16 by Andrew W-I Panel Member (23,900 points)