NEC3 Option A - Working Area and defined cost of design.

0 votes
40 views
We are using a NEC3 Option A, and have Hourly rates for defined cost of design outside the working area, which details various staff titles from our designer.

When we are quoting a CE, we use these rates form Design time, but is there any mechanism for recovering designers time for specific staff members that are not detailed in the Contract Data Part 2 ??
Thanks.