The Supervisor has instructed the Contractor to search for a defect and no defect is found. Is this a compensation event?

+1 vote
393 views

The Supervisor has instructed the Contractor to search for a defect and no defect is found. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Until the defects date, the Supervisor may instruct the Contractor to search for a Defect (see Clause 42.1). If no defect is found and the Contractor has given sufficient notice of doing work obstructing a required test or inspection, then the event is a compensation event (see Clause 60.1 (10)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)