Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,447 questions

5,841 answers

1,296 comments

Register its Free

Download here

NEC ECC: Option B compensation event pricing

0 votes
123 views
When pricing a CE in Option B, if existing rates from the BoQ are used to value the CE should the direct fee % be added to the valuation?
asked Aug 31, 2019 in Compensation Events by Broadhursts (120 points)  

1 Answer

+1 vote
The contract says "If the Project Manager and Contractor agree, rates and lump sums may be sued to assess a compensation event".

So, as a Contractor - which I am guessing is what you are - using straight rates from your BoQ don't cover your costs because, for example, there is a time related element or you have just bid low, then don't agree. If they are there for thereabouts, agree.

Identical wording is used in option A where there are not any BoQ rates at main contract level, but might be at subcontract level, so it is not unusual for Subcontractor BoQ rates to be used for the direct costs, Defined Costs for any Contractor costs plus relevant Fees.
answered Sep 1, 2019 by Jon Broome Panel Member (60,950 points)