Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,447 questions

5,841 answers

1,296 comments

Register its Free

Download here

NEC ECC: Use of rates and lump sums to assess a compensation event

0 votes
138 views
A Contractor has submitted a quotation for a CE using rates from the BQ. The contract is an NEC3 ECC Option B. The PM has not disagreed to the use of rates.

The quantity is incorrect and we have assessed the CE by changing the quantity and leaving the rate the same. The contractor has replied that the agreement to use rates only applies to their quotation, and that they do not agree to the use of rates in our PM assessment.

We believe cl. 63.13 concerning agreement to use rates and prices is a principle that can be applied to all assessments of that specific CE. It would not be equitable if the PM couldn't assess an incorrect CE on the same pricing basis as a contractor.

What would your views be?
asked Aug 19, 2019 in Compensation Events by MarkR (280 points)  

1 Answer

0 votes
Ideally, both Parties have a discussion about whether to use rates and lump sums to assess a compensation event before it is submitted.

Looking up "agree" on my on-line dictionary, it says "have the same opinion about something" and "concur; be of the same mind/opinion".

You are clearly not now of the same mind/opinion, so you are not agreeing, so you default to clause 63.1.
answered Aug 19, 2019 by Jon Broome Panel Member (60,950 points)