Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,326 questions

5,703 answers

1,262 comments

Register its Free

Download here

NEC ECS: Not received signed option A subcontract

0 votes
57 views
We have agreed NEC 3 Option A Subcontract terms and conditions via email with a Subcontractor. However we have still not received the Subcontractors signed subcontract.

The Subcontractor has proceeded with design as per the agreed Activity Schedule and have now issued a payment application for the completed works.

It’s my view that without a signed subcontract we cannot pay for the works as we are technically not in contract?
asked Aug 19 in Payment by trauts80 (420 points)  

1 Answer

+1 vote
You are both in contract when both Parties start acting as if you are in contract: the problem comes if the written draft contract has been going back & forth between the Parties and it is unclear when both Parties starting acting as if they were in contract and hence which 'draft' is actually the contract.

So if you respond and authorise the payment, you would definitely be in contract, but you may well have done actions before this and hence be in contract.
answered Aug 19 by Jon Broome Panel Member (59,440 points)  
Just to add to Jon's answer, if the works are deemed to be 'construction operations', as defined by s105 of the HGCRA 1996, as amended by the LDEDCA 2009, (together the 'Construction Act'), then you have a statutory obligation to implement a payment procedure irrespective of whether you have a formal written contract in place.