The Project Manager has withheld an acceptance. Is this a compensation event?

+1 vote
457 views

The Project Manager has withheld an acceptance. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager may withhold acceptance of a submission by the Contractor and withholding acceptance for a reason stated in the contract is not a compensation event (see Clause 13.8). However, if the Project Manager withholds acceptance for a reason not stated in the contract and other than acceptance of a quotation for acceleration or for not correcting a Defect, it is a compensation event (see Clause 60.1(9)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)