Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,429 questions

5,815 answers

1,292 comments

Register its Free

Download here

NEC4 ECC: PM late to instruct contractor to submit a quoation for the compensation event

0 votes
35 views
The Project Manager does notify this as a compensation event and instructs the Contractor to submit a quotation. The Contractor informs the Project Manager, 2 weeks after being instructed to submit a quotation for the compensation event, that it is impossible to meet the 3-week deadline.
The quotation is eventually submitted within the original 3 week period.

1. How should the Project Manager respond?

2.d.    The Project Manager fails to reply within 2 weeks and the Contractor notifies the Project Manager that the quotation is consequently deemed to be accepted. Is this correct?
asked Aug 15, 2019 in NEC3 and NEC4 Contracts by Hemen Wong (280 points)  

1 Answer

+1 vote
Hemen, this sounds too much like an exam question for us to answer. The "2.d." also indicates it is an exam question.
answered Aug 16, 2019 by Jon Broome Panel Member (60,890 points)