Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,201 questions

5,563 answers

1,215 comments

Register its Free

Download here

NEC3: Should you Implement 2 Contract Datas with one Form of Tender

0 votes
44 views
Would I be right in thinking, where there is one form of tender but 2 contract data (i.e 2 individual sections of road) then each one is administered separately, or should it be as one contract? I am trying to get to where LDs apply (say 1000 each/day) then should these be to the individual section (possibly compounded) or remain as 1000/day for the ‘whole’ contract. It seems to me like sectional completion should apply rather than separate CDs? or is there another reason?
asked Aug 15 in NEC3 and NEC4 Contracts by Dean Thomas (240 points)  

1 Answer

0 votes
sounds messy, there should be one Contract Data, Part 1 completed by the Employer, Part 2 completed by the Contractor
answered Aug 16 by dave bates Panel Members (13,850 points)