Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,424 questions

5,807 answers

1,290 comments

Register its Free

Download here

NEC ECC: Assessing CE delays against our own delays

+1 vote
106 views
A compensation event was notified in May, but due to getting authorisation etc... it will not be started until August. Our last accepted programme was in April.
In that time we have suffered our own delays.
As the CE came first can we impact the last accepted programme at the time of the compensation event increasing our EoT?
Or do we have to use the most current "as-built" information up to the point we'll start the works, and get no EoT?
asked Aug 6, 2019 in Time by rallp (210 points)  

1 Answer

+3 votes
You still assess the CE as a forecast at the point when it is instructed/notified. If that was before a Contractor delay then yes that should be assessed first. Any of your own Contractor delay that couldn't be mitigated that you had already incurred between April (last Accepted Programme) and May (date event was instructed/notified) should be taken into account first, and then the effect of the Ce against that programme to see/justify entitlement.

It is anther example where it is good to agree CE's as quick as possible to avoid the issue of people wanting to use hindsight even if the contract does not say that.
answered Aug 6, 2019 by Glenn Hide Panel Member (78,720 points)