Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,868 questions

6,316 answers

1,502 comments

Register its Free

Download here

JCT: Notice to quit

0 votes
182 views
Under a current project with a public sector employer, we have submitted our valuations on time, they have been recommended for payment by the Client QS as correct, They have been certified by the Architect, the client has been invoiced accordingly. The client has came back after 31 days from the 2nd valuation being certified to say that the invoice should be given to the architect and NOT them as a client.
We are now due payment for 2 valuations to be clear.

What is my best redress? 7 Day notice?

JCT 2012 With Quantities
asked Aug 3, 2019 in JCT Contracts by dsmccrory (310 points)  

1 Answer

+1 vote
Assuming that there is not doubt who the Employer in the contract is, and that there are no amendments to the standard building contract that say to the contrary, the Employer is liable to pay the Contractor the certified amount as they did not issue a pay less notice in accordance with the contract (clause 4.12.5). You do though need to check the contract to see if an invoicing procedure has been inserted that makes submission of an invoice to the Architect a condition precedent to payment being made by the Employer.

Assuming not, then you are entitled to simple interest on the late payments (clause 4.12.6) and to give a 7 day notice of intention to suspend (clause 4.14.1).

Better to take this action now, in the early stages of the contract whilst the stakes are relatively low, rather than wait until you have serious cashflow problems later on.
answered Aug 6, 2019 by Neil Earnshaw Panel Member (31,100 points)