Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,374 questions

5,764 answers

1,278 comments

Register its Free

Download here

NEC ECC: Contract Date

0 votes
72 views
Identified and defined terms 11.2 (4) The Contract Date is the date when this contract came into existence.

is this the date when both parties have signed the contract? or when the Employer has accepted the Contractor's offer by issuing the contract to him to execute?
asked Jul 29 in Time by KevinMorley (1,000 points)  

1 Answer

+2 votes
 
Best answer
I'm not a big fan of this particular definition as contracts can come into existence in many ways.

You will need to apply the law on contract formation to establish when a particular contract came into existence. It could be when the parties sign the contract or it could be when one party makes an offer which is accepted by the other (such acceptance could be by conduct).

In your example, it would be when the Employer has accepted the Contractor's offer, but more would likely be needed than just sending the contract to be signed as that may be seen as a counter offer.

Each will turn on the particular facts.
answered Jul 29 by stevencevans (2,360 points)  
selected Jul 30 by KevinMorley