Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,374 questions

5,764 answers

1,278 comments

Register its Free

Download here

NEC ECC: Access dates not included in contract data

0 votes
59 views
1.    Our work is in two sections.
2.    The first section is 25 weeks with 5 weeks float.
3.    The duration's and access dates for the second section is down in the contact to be agreed later.
4.    Access for the second section will now be given to us in 5 phases.
5.    The first phase of the second section is a 2-week duration, and access is given to us on the 26th week.
6.    The first section has been delayed and planned completion is now shown in our programme at 28 weeks.
7.    A compensation event was raised against the first access date for the second section as access was not provided before the planned contact completion date in the contract.
8.    The contractor rejected the CE as our programme is showing planned completion at 28 weeks, and they can give us access on the 26th week for a 2-week activity, therefore there is no change to the prices.
9.    The further 4 access dates will be given to us at a later date.


Question 1. Does the programme matter? Is our entitlement based on the agreed dates in the contract data? 25-weeks.
Question 2. Should the CE cover all access dates and make assumptions on when the next dates will be given to us? Or should a CE be raised against each access date separately?
asked Jul 24 in Time by rallp (210 points)  

1 Answer

+1 vote
It looks like you are referring to the NEC ECS (Contractor accepting CEs) but the comments apply to both the ECS and ECC forms.

Firstly as access is stated to be 'agreed later' then I can only assume that you would need to agree with the proposed second section access dates, rather than just accept what is offered to you.

You need to show contract access dates in your programme although you can show a later date if that is more appropriate or it changes due to circumstances, such as a delay to a previous section.  This later access date is then used to assess a compensation event under clause 60.1 (2) for an Accepted Programme.

You don't say what caused the delay to the first section and whether it was a compensation event, although if the first access date for the second section was stated in your programme (as accepted) and it was not given then that is a compensation event.

In answer to your questions;

1.  The programme does matter as you can put your own required access dates (later than the contract access dates) in an Accepted Programme which become the 'measure' for a compensation event,  Any entitlement would, therefore, be based on the programme access dates.  From what you have said it looks like the first access date for the second section is dependant upon completion of the first section works,  If the delay (from week 25 to 28) was not a compensation event, then the Contractor could have stated that the CE arises from a fault of the Subcontractor, in not accepting the CE.

2. A CE notification should relate to an event, so each access date separately, where appropriate.

This is not an ideal situation with 'unknown' access dates but I appreciate that this does actually happen, giving rise to uncertainty and dispute, as is evident in your case.
answered Jul 25 by Andrew W-I Panel Member (24,810 points)