Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,102 questions

5,447 answers

1,162 comments

Register its Free

Download here

NEC ECC: Amendment to secondary clause wording such as X22

0 votes
31 views
We are entering into an ECI on an NEC4 and the X22 wording has been amended to accommodate enabling works as part of the stage 1.
Guidance whether the amending X22 is acceptable considering;

Early Contractor involvement (used only with Options C and E) The Z clauses previously published by the ICE for early contractor involvement in 2015 have now been directly incorporated as a new secondary option.  ECI permits the Client to appoint the Contractor at an early stage to input into the design process to innovate and eliminate risks to achieve better cost and time certainty for the works. However, this does not provide a framework for instructing enabling works, which would need to be done under a separate enabling works contract.
asked Jul 8 in Secondary X, W and Y options by GARYCOLLINSON (120 points)  
Please can you clarify the question you are asking Gary as it isn't clear? The best answer I can give based on what you've written is that it depends on the wording of the amendments that were made to X22.

Please log in or register to answer this question.