Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,326 questions

5,703 answers

1,262 comments

Register its Free

Download here

The Project Manager or Supervisor has changed a decision which he has previously communicated to the Contractor. Is this a compensation event?

+1 vote
343 views

The Project Manager or Supervisor has changed a decision which he has previously communicated to the Contractor. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

This is a compensation event (see Clause 60.1(8)). The Contractor notifies the Project Manager of the event as a compensation event.

answered Oct 10, 2012 by BuiltIntelligence (870 points)