Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,102 questions

5,447 answers

1,162 comments

Register its Free

Download here

NEC ECC: What can Contractor can do if the Payment Assessment by Project Manager is incorrect in previous month

0 votes
89 views
The Contractor manages to submit an application for payment to the Project Manager just prior to the assessment date. This highlights that the previous amount due for payment was incorrect and low by a significant margin.

Should the Project Manager take account of the application for payment? How should the shortfall in the amount due be dealt with and what are the implications?
asked Jun 14 in Payment by wing88 (190 points)  

1 Answer

0 votes
You don't say whether this is NEC3 or NEC4, as there is no requirement under NEC3 for a payment application to be submitted, although this is a common amendment, however the Project Manager is required to consider any application submitted on or before the assessment date.

From what you have said it looks like the Contractor expressly disagrees with the amount that the Project Manager previously certified.  The Project Manager, however, makes an assessment based upon the Price for Work Done to Date, the definition of which is different depending on what main option is used.

Under the requirements of the 'Construction Act' the Project Manager is acting as a 'specified person' and is obliged to notify the amount due and state the basis upon which that sum has been calculated.  Provided that has occurred then the only recourse for the Contractor is to formally dispute this, although hopefully you will be able to meet to discuss the difference between the amounts applied for and the amounts certified.
answered Jun 17 by Andrew W-I (20,060 points)