The Project Manager or Supervisor has given an instruction for dealing with an object of value or of historical or other interest found within the Site. Is this a compensation event?

+1 vote
342 views

The Project Manager or Supervisor has given an instruction for dealing with an object of value or of historical or other interest found within the Site. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

This is a compensation event (see Clause 60.1(7)). The Contractor notifies the Project Manager of the event as a compensation event. The procedure for dealing with objects of value or historical or other interest found within the Site is stated in Clause 73.1.

answered Oct 10, 2012 by BuiltIntelligence (870 points)