NEC3 ECC Schedule of Cost Compenents - Charges 4 - Specialist Services 43(h)

0 votes
218 views
What types of costs could be included as 'Specialist Services' under Charges (4 - 43(h)) within the Schedule of Cost Components?
asked May 15, 2019 in SOCC SSOCC by J. Hill (120 points)  

1 Answer

0 votes
This is a difficult category, not least because it comes under Charges and so must relate to a Charge, otherwise it would be an alternative cost component, such as People. or perhaps treated as a Subcontractor.  It must also be incurred to Provide the Works, which is the overriding requirement for the inclusion of any cost under the SCC.

What comes to mind is something like specialised weather forecast reports or local tidal information, which you can only obtain by paying for it (not publicly available), especially where works can only be undertaken during specified environmental conditions,

You could also include Met Office reports for weather, to assess whether a compensation event has occurred, as they come under this category of cost and fit with the definition of Provide the Works.
answered May 23, 2019 by Andrew W-I Panel Member (27,390 points)