Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,737 questions

6,154 answers

1,424 comments

Register its Free

Download here

NEC ECC: Option B Clause 63.13 - effect of amendments

0 votes
129 views
I have an NEC3 ECC Option B contract with an unusual amendment.

In Clause 63.13, the bullet point permitting "a changed rate" has been deleted in the list of amendments. 63.1, however, has not been amended.

 For CEs for which there is an item in the BQ (and the contract Schedule of Rates, which also has been inserted into the first bullet point of the amendments) for items of work not already done, does this mean that the rates in the BQ or SoR take precedence over any Defined Cost plus Fee valuation of the CE?
asked May 15, 2019 in Compensation Events by MarkR (280 points)  

1 Answer

+1 vote
Neither ! This clause is about how changes in the Prices - worked out under 63.1 - are inserted into the existing BoQ - see the opening sentence of 63.13.

What it does lead to, which I think you have picked up on, is a contractual dead-end in that if the work is of the same type and quantity as the BoQ, but done in different circumstances (say a more onerous constraint due to an instruction changing the Works Information) which makes it more expensive, then the contract is not clear about how the new rate is inserted into the BoQ.
answered May 15, 2019 by Jon Broome Panel Member (64,020 points)  
Yes, I was hoping that there might be some way of making this amendment work, but clearly - using the contract at least - there isn't!