Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,737 questions

6,154 answers

1,424 comments

Register its Free

Download here

NEC ECC: Item coverage in option B

0 votes
113 views
Just wondered if someone could settle an argument I currently have with a project manager based on an Option B with elements of contractor design for specialist structures series 2500. He said that if drawings provided at the tender stage do not show the "designated outlines" on the tender drawing then you do not know what to price within the structure item, for example foundations, expansion joints etc. And you could price virtually nothing in the tender item as you would get a CE due to poor contract documentation. I don't necessarily agree with this view as the design would show this level of detail but he firmly stands by his opinion of if there are no "designated outlines" you do not know what to price and he reckons he has successfully won this claim on previous contracts in the past.

Any comments appreciated
asked May 14, 2019 in Compensation Events by JPQBT (140 points)  
I think your question is actually about the method of measurement being used (which sounds like Method of Measurement for Highway Works) rather than the form of contract being used.

The only issue with regard to NEC is why you are using Option B if there is an element of the works (probably quite significant) which has not been designed to provide the level of detail that is really required for Option B?  It would seem to me that Option A would be more suitable.

1 Answer

0 votes
I can only answer this is generality as I do not have access to and am not familiar with the structure 2500 series or what "designated outlines" are

If the Works Information (NEC3) / Scope (NEC4) is vague, the Contractor can only price on what is in front of him in a minimal, but realistic manner. E.g. you show an outline of the structure, so I can assume that it would include for this, that and the other. So if the PM starts adding detail to that structure (it would be a compensation event) which the Contractor had not reasonably allowed for, then the Contractor could justify an increase in the Prices. That's the theory.

The problem with this approach is that the subjectivity/vagueness in the original description will undoubtedly cause arguments over what the Contractor should have reasonably allowed for.

Having said this, can you clarify whether the 'project manager' (small 'p' & 'm') is the Project Manager under ECC or another individual e.g. the Contractor's project manager and whether they are arguing for a big Price increase or none at all.
answered May 14, 2019 by Jon Broome Panel Member (64,020 points)