NEC PSC Is it possible to shorten the period for reply

+1 vote
108 views
It it possible to shorten the period for reply when an urgent situation arises?
What course of action is there when a consultant simply says "I have two weeks" within Contract Data.
asked Apr 19, 2019 in ReachBack FAQs by Kingfellow (250 points)  

1 Answer

+1 vote
The timescales in the contract are the maximum that should be taken. You would like to think if you explain why you need an answer quicker, in the spirit of the contract they would and especially if it is in their or the project interest to do so. However, no way to force this mid-contract. Contractually they have the timescale stated in the contract.
answered Apr 19, 2019 by Glenn Hide Panel Member (79,340 points)