Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,376 questions

5,766 answers

1,280 comments

Register its Free

Download here

NEC ECSC: is W1 a default option outside UK?

0 votes
112 views
Contract Data on an NEC3 ECSC has been left blank. The main NEC3 ECC applies W1 for dispute resolution.
There is no "flowdown" clause.
W2 not applicable in this jurisdiction.
Does W1 apply by default in the subcontract, or is there in fact no Dispute resolution option adopted?
asked Apr 17 in Secondary X, W and Y options by Big Al (240 points)  

1 Answer

0 votes
I assume you are referring to the Engineering and Construction Subcontract (ECS) rather than the Engineering and Construction Short Contract (ECSC).

Although the W Options are perceived to be optional, the intention is that they are not and one of these is chosen.  In NEC(1) and NEC2 the dispute resolution procedure was part of the conditions of contract at core clause 9.  

If the contract data doesn't state a W option then none would apply, regardless of what was in the main ECC contract., as they are discrete contracts.  In this instance you would be required to refer any disputed matter to the applicable legal process which applies in the jurisdiction under which the contract is subject to.
answered Apr 17 by Andrew W-I Panel Member (24,810 points)  
edited Apr 17 by Andrew W-I
yes
ECS
Acronyms will be the death of me.
Thank you.