Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,864 questions

6,305 answers

1,501 comments

Register its Free

Download here

NEC ECC: Termination for any reason

+2 votes
502 views
Clause 90.1 of  the NEC 3 ECC Contact allows an Employer to terminate for any reason. Are there any requirements that they must do so in good faith etc? Or can it be at will for for any reason at all even if it is unfair to the Contractor?
asked Mar 13, 2019 in Termination by adon (170 points)  

1 Answer

+2 votes
 
Best answer
It doesn't expressly state what the reason might be, although it wouldn't include one of the other specified reasons.

Where the Employer terminates for 'any (other) reason' the Contractor is paid amounts due A1 A2 and A4, with A4 essentially including 'lost profit', so the Contractor doesn't 'lose out' from whatever reason the Employer has used to terminate.

Whether it is 'fair' or not doesn't take away from the fact that the Employer is entitled to exercise this right under the contract.
answered Mar 14, 2019 by Andrew W-I Panel Member (27,560 points)  
selected Mar 15, 2019 by Neil Earnshaw