Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,008 questions

5,336 answers

1,102 comments

Register its Free

Download here

NEC ECC: People Costs Allowance Within the Fees

0 votes
127 views
Including within the fee is an allowance of 3 days for a QS. Assuming the QS works 5 days a week within the Working Area (Site), when assessing a CE under option C can I offset the QS cost already allowed for within the fee and assess the recoverable cost under Defined Cost as 2 days?
asked Mar 10 in Compensation Events by Ziggles (120 points)  

1 Answer

0 votes
What is in your fee is actually irrelevant.

To assess whether you get anything extra for a CE, you have to demonstrate the change in Defined Costs due to the CE. So if the QS is based in the Working Areas for 5 days a week and has to work a bit late due to a CE, but doesn't get any over time, then there would be no effect.
answered Mar 10 by Jon Broome (53,290 points)