Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,912 questions

5,237 answers

1,011 comments

Register its Free

Download here

NEC ECS: Is there a limit to the change in scope that can be instructed under the contract?

+1 vote
66 views
Is there a limited to what amount of variation can be instructed via an NEC3 contract? E.g. if a subcontract included specific exclusions when awarded and the PM accepted the Subcontractor on that basis (that certain activities would not be delivered via this subcontract), can these tasks still be instructed if the Contractor and Subcontractor subsequently agree to undertake some of them through CE's?
asked Mar 7 in General by PM10101 (290 points)  

1 Answer

+1 vote
Let's take this question in generality first : your contract is deliver to deliver the 'works' (in italics). So, to take a real life example, if the 'works' were for 'The construction of X' and then the Employer wanted to add in design, you would have a very good argument for saying something like "No, the scope of my contract is for 'construction of X' and does not include design, so I don't have to do it."

However, in the legal interpretation of a contract, detail over-rides generality, so if the original Works Information (the detail !) already had some design in it, you would not be able to sustain an argument that you didn't have to do the pre-existing design. If the PM instructed new work of a similar nature was introduced for which the Contractor had to do similar amount of design, then the Contractor would probably still have to do it. But if new work was introduced which had greater levels of design or was of a different nature, then it would become more subjective.

In your subcontract, from what you say, it seems that the Contractor  is instructing work for which there were specific exclusions so the understanding of the Parties was that these were NOT within the definition of the 'works'. But the big Question for me, is what legal status do these exclusion have i.e. were they written down ? In which document - form of agreement, subcontract data, Works Information (Contractor's or Subcontractor's) etc. Without knowing this, it is hard to give a definitive answer.
answered Mar 8 by Jon Broome (51,860 points)  
The Contractor is part of a 4 way JV and the Subcontractor is a division of one of the JV members. The exclusions as referred to were detailed as subcontractor clarifications included within the CD Part 2 of the subcontract in question. The PM for the main contract was content to see these exclusions as the bofq had no coverage for the items and to instruct through CE's it was deemed would be very costly. Subsequently the Contractor has instructed some of these to the Subcontractor and costly CEs have been included in applications. The main contract is an option C.
Well that's good from your perspective because the Contract Data almost certainly has precedence over the Works Information, especially changed Works Information. Have a look at this article, originally published in the NEC User's Group Newsletter in July 2008, Issue 46 and then go and wave it in the Contractor's face ! https://www.jonbroome.com/getattachment/44704d3b-547d-4bd9-a278-b40389ffcc58/Is-there-a-hierarchy-of-documents-under-the-ECC.aspx