NEC ECC: Acceptance of contractor's latest submitted Cl32 programme vs previous submission

+1 vote
116 views
If an Employer accepts a contractor's latest Cl32 programme submission, does this imply, by default, that previous submissions of Cl32 are also accepted, despite not having formally been accepted?

In other words, can a contractor accept Feb-19 Cl32 programme but rejects  a Jan-19 Cl32 one?
asked Mar 7 in Time by Prefole (210 points)  

1 Answer

+1 vote
Absolutely they can. There may have been fundamental issues that have now been corrected which has led to Feb being accepted. Jan will remain unaccepted.

You could go back and try to amend the Jan programme to get a revised version of that programme retrospectively accepted but it serves little purpose and you can make better use of your time/resources. The only issue then is you have a two month gap (assuming the Dec programme was accepted) in order to assess compensation events that occurred then which might now be a little bit more subjective.

You cant turn the clock back now, but much better would have been to revise the Jan programme within a day or two of it being rejected and then sit down with the Employer to explain the changes made and if there is anything else wrong, to get a revised version then still accepted in January.
answered Mar 7 by Glenn Hide Panel Members (74,800 points)  
Thanks Glen, I wrongly thought that the latest accepted version will supersede all previous versions, the latter becoming accepted 'by default.