Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,912 questions

5,237 answers

1,011 comments

Register its Free

Download here

NEC ECC: Contractor change to Works information

+2 votes
44 views
NEC ECC Option C. Contractor changes methodology from that priced for and stated in their tender. As a result of this, obstacles such as poor ground and services, which would not have been a problem should the tender methodology been followed, became a problem for the revised method of work.
Is this a Compensation Event?
asked Mar 7 in Compensation Events by ernie.spence (140 points)  

1 Answer

+1 vote
Yes - this would be a compensation event, and more importantly no contractual clause that says "unless you changed your method of working".
answered Mar 7 by Glenn Hide (70,150 points)