Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,008 questions

5,336 answers

1,102 comments

Register its Free

Download here

NEC ECC: Rejecting PMI's under Option C

+1 vote
103 views
Working under an NEC3 ECC Option C contract as the Contractor, we have received a PMI that we do not want to take ownership of. Under NEC3 is there a way for the Contractor to reject a PMI and how does the Contractor go about rejecting this PMI or CE?
asked Feb 28 in Compensation Events by kchastney (190 points)  

1 Answer

+1 vote
You are required to comply with an instruction if it is valid under the contract and relates to the works you have contracted to provide (as defined in Contract Data Part 1) unless to do so would mean you were to commit an illegal act.

If you have concerns over the instruction you should discuss them with the PM and see if a solution could be found.
answered Mar 1 by dave bates (12,500 points)