NEC ECC: Option C - Off Site Fabrication - Sub-Contract Fee or Direct Fee?

0 votes
83 views
If a Contractor under an Option C issues an NEC3 Supply Contract for some off site fabrication does this attract the sub-contract fee % or the direct fee % in their applications?
asked Feb 22 in Payment by reachbackinterloper (120 points)  

1 Answer

0 votes
The off site fabricator would fall as a subcontractor under clause 11.2 (17) since it is constructing part of the works. The Subcontract Fee % would therefore be applicable.
answered Feb 25 by dave bates (12,500 points)