Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,746 questions

6,164 answers

1,427 comments

Register its Free

Download here

NEC ECC: Termination & Pain Gain calculation

0 votes
202 views
Under an NEC3 ECS Main Option C, If the works were terminated by the Contractor or Subcontractor, will the pain gain mechanism still apply to the final amount due?
asked Feb 21, 2019 in Termination by Yahik (410 points)  

1 Answer

0 votes
Yes.  Main Option C adds clauses 93.4 and 93.6 which detail how the share amount is assessed, which is then added (or deducted as the case may be) to the calculated total.
answered Feb 21, 2019 by Andrew W-I Panel Member (27,470 points)