I assume you are the main Contractor. The delays caused by Subcontractor B are a compensation event under subcontract for A : this could, for example, be under 60.1 (2), (3) or (5) and are consequently put back by the time effected: see the second sentence of clause 63.3.
Subcontractor A then has the obligation to hit these revised Key Dates.