Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,265 questions

5,634 answers

1,244 comments

Register its Free

Download here

NEC ECC: Option A - Design in Compensation Events

0 votes
160 views
When assessing a compensation event under the NEC3 Option A Contract how do you correctly apply the relevant fees to design costs?

The contractor directly employs a designer (off-site) and has reasonably forecast defined cost for design within their CE quotation.

Within the Contract Data Part 2 there is a prescribed design overhead percentage.

In assessing the design costs in this instance do you:

1. Apply only the design overhead percentage.
2. The design overhead percentage then the direct fee percentage.
3. The design overhead percentage then the subcontract fee percentage.

In the instance of 2 and 3 is the direct/sc percentage applied to the defined cost element only to avoid fee-on-fee?
asked Feb 7 in Compensation Events by kje537 (120 points)  

1 Answer

0 votes
The answer would depend on whether the designer is a Subcontractor or not.

If 'No', then 2. above applies.

If 'Yes', then 3. above applies.
answered Feb 7 by Jon Broome Panel Member (58,140 points)