Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,864 questions

5,179 answers

966 comments

Register its Free

Download here

NEC ECS: Carrying out Works While in Disagreement

0 votes
83 views
If there is an element of works that the Main Contractor and Subcontractor disagree on responsibility ie subcontractor says he hasn't included and isn't responsible under his interpretation of the documents and the Main Contractor thinks the subcontractor is, does the subcontractor have an obligation to carry out the works? Or can he refuse?

I'm thinking that issuing an instruction to the subcontractor would be the course of action, noting that it does not change the Works Information.
asked Feb 5 in Compensation Events by BulletproofQS (120 points)  

2 Answers

0 votes
It looks like you have answered your own question.

The Contractor gives an instruction under clause 17.1, which the Subcontractor is obliged to obey, in accordance with the obligation under clause 27.3.

If the Subcontractor still believes this is outside the Scope then the matter should be referred as a dispute, although probably better to sit down together firstly and for the Subcontractor to explain why they believe the work is not included in the Scope.
answered Feb 6 by Andrew W-I (15,030 points)  
0 votes
Yes you should instruct the Subcontractor to carry out the works even if you believe that it is already in their Scope, and under 27.3 they would be obliged to follow it unless it is illegal, impossible or outside their competencies. If the Subcontractor does not believe it to be part of their Works Information (or Scope under NEC4) then they can notify that they believe it to be a compensation event, presumably under 60.1(1). If the Contractor believes it is not one, they would respond stating why not. The only official remedy at that point would be senior representatives under NEC4 or adjudication under NEC3 if they clearly believe it to be one.
answered Feb 7 by Glenn Hide (68,950 points)