NEC ECC: Does an ambiguity in the BoQ permit the Contractor to notify a compensation event?

0 votes
52 views
Excavation depths not identified in BoQ as method of measurement requires
asked Feb 2 in Compensation Events by moorej (170 points)  

1 Answer

0 votes
NEC3 Option B provides for a CE in the case of an ambiguity in the BoQ, see clause 60.6
answered Feb 3 by dave bates Panel Members (13,630 points)