Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,959 questions

5,287 answers

1,051 comments

Register its Free

Download here

NEC ECC: Should an NEC3 Option C Contractor be applying for Inflation (X1) to their NEC3 Option A Subcontractor's 'costs'?

0 votes
54 views
I represent the client and the Contractor is working under an ECC
asked Jan 31 in Secondary X, W and Y options by ASimpleQS (370 points)  
edited Feb 1 by ASimpleQS

1 Answer

+1 vote
The answer is NO as X1 operates to add an inflationary adjustment amount to the Prices (target) based on the value of an interim assessed amount of PWDD due.

The adjustment to the Prices is made based on when cost is actually incurred, by applying a Price Adjustment factor (PAF) calculation, which compares the current indices  with the Base Date Indices (as stated in the Contract Data).
answered Feb 1 by Andrew W-I (17,070 points)  
Thanks for your answer... in theory the Contractor's PWDD will include works associated with their Subcontractor's Option A Subcontract Agreements... on that basis it sounds like whether they award their Subcontract agreements under an A, C etc. is irrelevant?