NEC4 ECC Clause X22 (ECI)

+1 vote
84 views
What would be the best way for a Contractor to engage a designer on an NEC4 ECC Option C Contract, where the Contractor is designing the whole of the Works and where the Contractor requires the designer to undertake works for the ECI Stage One Scope?

Would a NEC4 PSC or PSS be more suitable; and does X22 exist in both Contracts?
asked Jan 31 in Secondary X, W and Y options by philjbrady (600 points)  

1 Answer

+2 votes
 
Best answer
The Professional Service Subcontract would be most suitable as the timescales would fit in with the main Engineering & Construction Contract (ECC).

Neither the NEC4 PSC or PSS has an X22, but it would be relatively easy to take the ECC's X22 and adjust IF the Contractor is willing and the project circumstances fit. As a general comment on X22, I do not think it has sufficient termination provisions if a Client decides not to proceed to Stage 2, especially if they wish to use another contractor.

Alternatively, the Contractor - who is not subject to EU rules for procurement - could let one PSS contract for Stage 1 and once Stage 2 is confirmed, let another PSS contract to the same Consultant for Stage 2.
answered Jan 31 by Jon Broome (52,270 points)  
selected Feb 6 by philjbrady