NEC ECC: How does clause 25.2 work in practice under option C?

0 votes
87 views
If the Employer has incurred costs as a result of the Contractor not providing the services, how in an option C does the amount get paid by the Contractor. Is it as simple as the PM deducting the costs from his assessment i.e. in line with clause 50.2 third bullet?
asked Jan 31 in Payment by PM10101 (440 points)  

1 Answer

+1 vote
Yes that is correct, although entered on a payment certificate (notice) as a 'below the line' adjustment, in that it is not included in any calculation for retention or VAT.

As it is not PWDD it would not be included in a share calculation either.
answered Jan 31 by Andrew W-I (17,470 points)