Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,326 questions

5,703 answers

1,262 comments

Register its Free

Download here

FIDIC Red Book: Clause 20.1 and Determination

+1 vote
162 views
Sub-clause 20.1 indicates in the 6th paragraph that the Engineer may make detail comments if the Contractor's claim is disapproved.

Two paragraphs later, sub-clause 20.1 states that the Engineer proceeds in accordance with sub-clause 3.5.

A Contractor has insisted on the Engineer's determination of a claim that the Engineer has disapproved. Does the Engineer proceed with sub-clause 3.5 if a claim is disapproved?

If the Contractor is not able to provide sufficient particulars to demonstrate the basis of claim is there further need for the Engineer to act under sub-clause 3.5 after giving details comments?

The Contractor can refer the Engineer's disapproval as a dispute under sub-clause 20.3. Is that the proper contractual procedure for the Contractor if the Engineer's decision under sub-clause 20.1 is not satisfactory?
asked Jan 28 in Construction Contract Red Book by MCH (240 points)  

1 Answer

0 votes
Clause 3.5 is the process of making a determination to be followed whenever the contact requires a determination to be made.

The disapproval of the Engineer under the 1999 or 2017 versions should have been in accordance with clause 3.5. There is no longer, as there was under older FIDIC forms, the requirement for an Engineer's Decision, you simply move on to DAB, Amicable Settlement and/or Arbitration
answered Feb 27 by Rob Horne Panel Member (19,700 points)