Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,175 questions

5,531 answers

1,204 comments

Register its Free

Download here

NEC ECC: Any liability issued defining quantities within an Activity Schedule?

+1 vote
81 views
A contract was awarded using ECC Option A. The Employer left tenderer's free to define the activities on their activity schedule.What are the possible disadvantages if the Employer had defined the activities on the activity schedule?
asked Jan 25 in General by moorej (170 points)  

1 Answer

0 votes
The risk of errors in the activity schedule remain with the Contractor. The activity schedule is not Works Information. Changes in the wording of quantity in the activity schedule on their own are not compensation events.

The contract does not expect the Employer to have written the activity schedule, so the Contractor needs to verify anything written as they will take responsibility. It would be useful if the Employer makes it clear that the Contractor should add/change anything in the activity schedule and break it into their own level of detail.
answered Jan 25 by Glenn Hide Panel Members (74,860 points)